Direct answer
A comparable API 5L quotation needs the governing standard and edition, PSL, grade, outside diameter, wall thickness, length and ends, quantity, coating, inspection and document scope, destination port and delivery term. Missing any one of these changes the manufacturing route, test scope or commercial basis. A price built from a partial description is not a comparable offer.
This checklist is for buyers, EPC procurement teams and trading companies preparing an enquiry for API 5L line pipe or API 5CT casing and tubing. Its purpose is to make competing quotations answer the same technical and commercial question.
The minimum data a pipe supplier needs
Use one row per pipe specification. If the project has a line list, tender extract or piping class, attach it as well; the table below lets the supplier confirm how it read the requirement.
| RFQ field | What to state | Why it changes the offer |
|---|---|---|
| Product and governing standard | API 5L line pipe, API 5CT casing/tubing or another product; include the standard edition and purchaser specification. | The edition, design code and purchaser specification can add requirements beyond the general product description. |
| PSL and grade | PSL1 or PSL2; steel grade such as B, X42, X52, X60, X65, X70, J55, K55, N80, L80 or P110 as applicable. | Chemistry, testing, impact and documentation controls can differ by product level and grade. |
| Dimensions | Actual outside diameter and wall thickness, or the exact NPS/DN and schedule where the standard permits that designation. | Wall thickness and diameter determine weight, mill capability, forming route and loading plan. |
| Length and ends | Random or fixed length, target length, tolerance and whether ends are plain, bevelled, threaded or coupled. | Cutting yield, end preparation and coupling selection affect production and packing. |
| Construction route | Seamless, LSAW or another route where the project requires one; otherwise state whether the route is open for supplier review. | Different routes have different size, grade and testing limits. |
| Quantity | Metric tonnes, metres and piece count where available; state whether mixed sizes are allowed. | Production scheduling, price and freight depend on total weight and the number of line items. |
| Coating or lining | 3LPE, 3LPP, FBE, internal epoxy or another system, with the governing coating specification and thickness requirement. | A coating name alone does not define the system. Coating is normally quoted and inspected separately. |
| Testing and inspection | Hydrostatic, NDT, impact, HIC/SSC, dimensional inspection, third-party witness points and any purchaser specification. | Test scope changes processing time, recoveries, documentation and third-party cost. |
| Documents | EN 10204 3.1 or 3.2 requirement, ITP, MTC language, coating report, packing list, certificate of origin and other project documents. | A mill certificate and buyer-nominated third-party inspection are separate controls. |
| Commercial baseline | Incoterm, named port, required delivery period, quotation currency, validity and payment proposal. | FOB China, CIF destination and ex-works offers are not directly comparable. |
A usable line-list example
The following format is enough for a supplier to identify most deviations before pricing. It is not a substitute for the project specification.
| Item | Example entry |
|---|---|
| 1 | API 5L PSL2, X52QS, seamless, OD 323.9 mm x WT 12.7 mm, bevelled, 12 m, 500 t, 3LPE, EN 10204 3.1, FOB Tianjin |
| 2 | API 5L PSL2, X60, LSAW, OD 914 mm x WT 15.9 mm, bevelled, 12 m, 800 t, FBE, third-party inspection, CIF Jebel Ali |
| 3 | API 5CT PSL1, K55, 244.5 mm x 8.94 mm, BTC, R3, 2,000 joints, painted with couplings, FOB any Chinese port |
The gaps that most often invalidate a quotation
- Wall thickness without outside diameter. The supplier cannot calculate weight, production route or loading without both dimensions.
- “3LPP” without a coating specification. Coating type, thickness, cutback, adhesion, impact and repair requirements must come from the governing standard or project specification.
- “ADNOC approved” without the approved-manufacturer list. Approval is normally tied to a manufacturer, product scope and project basis. Ask which legal manufacturer and which document control the requirement.
- One sample joint treated as a production order. A small quantity question must be separated from the expected project quantity, because stock availability and production pricing are different offers.
- Inspection left as “normal.” State whether the buyer needs MTC only, document review, witness points, NDT, special tests or a buyer-nominated inspection agency.
What the supplier should return
A useful response should identify the offered mill and production route, confirm the applicable grade and dimensions, state coating and inspection scope, list deviations, show the Incoterm and named port, and separate included and excluded items. If the response cannot name those items, it is not comparable even when the headline price looks lower.
Use the RFQ to improve the next conversation
The checklist is also a qualification tool. If a buyer cannot provide the line list, project specification, final user or delivery basis, ask for the missing decision rather than creating several speculative price versions. This protects both sides from comparing offers built on different assumptions.
For product scope, start with the API 5L line pipe overview, the PSL2 seamless guide or the API 5CT casing and tubing page. For documents, use the inspection and document checklist.