Direct answer
HIC and sulfide stress cracking requirements must be defined by the project service conditions and governing specification. Do not rely on the phrase “NACE compliant” alone. Confirm the applicable NACE MR0175 / ISO 15156 basis, material condition, test method, acceptance criteria, sample location, heat-treatment controls, third-party inspection and documents required for the actual order.
Hydrogen-induced cracking and sulfide stress cracking are material-risk controls. They supplement the product specification; they do not replace API 5L dimensional, chemical, mechanical or inspection requirements.
Understand the three procurement terms
| Term | What it addresses | What the RFQ must define |
|---|---|---|
| HIC | Hydrogen-induced cracking in a wet sour service environment. | Applicable standard/test method, solution, sample orientation, acceptance criteria and number of tests. |
| SSC | Sulfide stress cracking under tensile stress and a sour environment. | Material condition, stress level and test method where required by the project specification. |
| NACE MR0175 / ISO 15156 | Material selection and qualification requirements for oil and gas service in H2S-containing environments. | Which part/applicability is invoked, the project-defined environment and the evidence accepted for the material. |
Service data needed before a supplier can confirm the route
- Product standard, grade, PSL and construction route.
- Actual OD, wall thickness and line-list quantity.
- H2S partial pressure, pH and other corrosive conditions defined by the purchaser.
- Design temperature, pressure and any heat-treatment condition.
- Required HIC/SSC standard, method and acceptance criteria.
- Test sample location, frequency and heat/lot traceability.
- Third-party witness, NDT, MTC and project data-book requirements.
Use precise RFQ language
Instead of writing only “HIC & SSC resistant”, provide a controlled requirement such as:
The exact methods and limits must come from the project specification and the current applicable edition. This guide does not substitute for those documents.
Evidence to request with the quotation and order
- Manufacturer’s material route and heat-treatment control.
- Proposed test standard, frequency and sample location.
- Acceptance criteria tied to the project specification.
- ITP showing witness and hold points.
- EN 10204 MTC and separate HIC/SSC test reports.
- Third-party inspection scope where required.
- Heat/lot traceability from production to final report.
How this changes quotation comparison
Two offers can show the same grade and size while one excludes special testing, one assumes a different material condition and another includes third-party witnessing. Normalize these items before comparing price. Use the quotation comparison guide for the commercial normalization.
Questions to close before the price is final
- Is the requirement based on the line-pipe purchase specification, a project material specification or a separate sour-service document?
- Does the requirement apply to every heat, a defined frequency or only selected production lots?
- Which product form and heat-treatment condition are being qualified?
- Will the test reports identify the heat, pipe and test location clearly enough for traceability?
- Are retest rules and the treatment of nonconforming heats defined?
- Does a buyer representative or third-party agency need to witness sampling and testing?
These questions often reveal that a “minor” test clause changes the production route or the acceptable mill. Resolve them before comparing unit prices.
Confirm the material route first
Start with the PSL2 seamless pipe page or LSAW pipe page, then use the inspection and document guide to define the evidence pack. Include the service data and project specification in the enquiry.